When should submissions for the Design Rating be made?

Prepare for the Estidama Test with our engaging quizzes. Access flashcards, multiple choice questions, and detailed explanations to excel in your exam. Start today!

Submissions for the Design Rating should be made at the end of the construction documentation stage because this is the point at which the project's designs are finalized and detailed enough to assess their adherence to the Estidama standards. This stage includes comprehensive documentation that illustrates how the project meets sustainability criteria, enables clear evaluation of design intent, and allows for verification that the proposed measures will achieve the desired sustainability goals.

Making submissions at this stage also allows for feedback from the Estidama reviewing body to ensure that any necessary modifications can be made before construction begins, thereby integrating sustainable practices appropriately from the outset. Other stages mentioned may not provide the necessary level of detail or completed design to undergo a thorough assessment, which is crucial for the effectiveness of the submission process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy